- Uncategorized (58)
- 26. January 2012: thanks for the trailways
- 2. July 2011: Dutchess Rail Trail south
- 26. April 2011: Dutchess Rail Trail
- 8. April 2011: Hudson Valley Rail Trail
- 7. November 2010: Hudson Valley Rail Trail phase 2
- 9. October 2010: Dutchess Rail Trail - phase 3 construction
- 20. September 2010: Hudson Valley Rail Trail - phase 2 construction
- 15. September 2010: Labor Day Weekend 2010
- 10. September 2010: Hudson Valley Rail Trail - phase 2 construction
- 25. August 2010: Hudson Valley Rail Trail - phase 2 construction
Dutchess Trailways update
05/15/09
DUTCHESS RAIL TRAIL
northern terminus - Morgan Lake C.O.P. - see paving equipment in parking lot - trail ROW at this end still not paved yet - work on trail head sign roof etc.
WALKWAY OTH
east end C.O.P. - no trailers etc. off Parker Ave. (SR 9G) railings on both sides up to near Dutchess Ave. just behind big green crane - there now is scafolding just below that last section of decking from 3 weeks ago - there is an I beam going transversly across the bridge just in front of the big crane - there are trafic cones blocking sidewalk underneath
west end Highland - decking now out over water - work was in progress 15:00 hrs. saw the big crane being swung around - there is scafolding around the second bent in the water from west end I could see workers and could hear jack hammer or very big impact tool/gun and saw a barge in the river at the pier/footing for this bent- I had noted a wider section of decking over (active) CSX RR along river near river level